• reFRESH Fort Myers Beach Projects

    water main • sanitary sewer force main •  storm drainage • sidewalk and roadway streetscape

    Learn More

Click here for the Latest News and Documents.
http://refreshfmbeach.com/wp-content/uploads/2018/11/refresh-blvd-logo-horz-289x84.png

This week, the reFRESH Estero Boulevard active work zone is from Strandview Avenue to Albatross Street. Motorists should expect travel lanes on Estero Boulevard to be shifted from Strandview Avenue south to Albatross Street. Two travel lanes will remain open the majority of the time; however, intermittent lane closures may be necessary. Motorists should use caution.

http://refreshfmbeach.com/wp-content/uploads/2018/11/reFRESH-Logo-Wide-250x84.jpg

reFRESH Waterlines crews are installing water main on both sides of Estero Boulevard from Albatross Street to the south end of the Island and installing connections to side streets. New water main and storm drainage are being installed on Phase 4 side streets.

//refreshfmbeach.com/wp-content/uploads/2019/09/refreshFMBsegmentmap9.25.19.jpg

Estero Boulevard Project Segment Progress

Monitor construction progress for each segment of the project, including progression of the installation of the water main, sanitary sewer force main, storm drainage, roadway and sidewalks.

Segment 1 - Crescent Street to Lovers Lane100%

sanitary sewer force main

water main *

storm drainage

roadway

sidewalks

Segment 2 - Lovers Lane to Strandview Avenue100%

sanitary sewer force main

water main *

storm drainage

roadway

sidewalks

Segment 3 - Strandview Avenue to Lanark Avenue72%

sanitary sewer force main

water main *

storm drainage

roadway

sidewalks

Segment 4 - Lanark Avenue to Albatross Street 41%

sanitary sewer force main

water main *

storm drainage

roadway

sidewalks

Segment 5 - Albatross Street to Bay Beach Lane10%

sanitary sewer force main

water main *

storm drainage

roadway

sidewalks

Segment 6 - Bay Beach Lane to the end of the island5%

sanitary sewer force main

water main *

storm drainage

roadway

sidewalks

* Water main construction is handled by the Town of Fort Myers Beach with the reFRESH Fort Myers Beach Waterlines Project and progress may be completed prior to the reFRESH Estero Boulevard Project segment beginning.