This week, the reFRESH Estero Boulevard active work zone is from Strandview Avenue to Albatross Street. Motorists should expect travel lanes on Estero Boulevard to be shifted from Strandview Avenue south to Albatross Street. Two travel lanes will remain open the majority of the time; however, intermittent lane closures may be necessary. Motorists should use caution.
reFRESH Waterlines crews are installing water main on both sides of Estero Boulevard from Albatross Street to the south end of the Island and installing connections to side streets. New water main and storm drainage are being installed on Phase 4 side streets.
Monitor construction progress for each segment of the project, including progression of the installation of the water main, sanitary sewer force main, storm drainage, roadway and sidewalks.
Segment 1 – Crescent Street to Lovers Lane100%
Segment 2 – Lovers Lane to Strandview Avenue100%
Segment 3 – Strandview Avenue to Lanark Avenue72%
Segment 4 – Lanark Avenue to Albatross Street 41%
Segment 5 – Albatross Street to Bay Beach Lane10%
Segment 6 – Bay Beach Lane to the end of the island5%
* Water main construction is handled by the Town of Fort Myers Beach with the reFRESH Fort Myers Beach Waterlines Project and progress may be completed prior to the reFRESH Estero Boulevard Project segment beginning.
Questions? We’re here to help! Submit your questions through our contact form.
Phone: 239-337-1071 | Toll Free: 1-877-496-1076 | Email: info@REFRESHFMBeach.com
All information and graphics are subject to change. © Copyright 2018 reFRESH Estero Boulevard