• reFRESH Fort Myers Beach Projects

    water main • sanitary sewer force main •  storm drainage • sidewalk and roadway streetscape

    Learn More

https://refreshfmbeach.com/wp-content/uploads/2018/11/construction-look-ahead-289x84.png

Week of September 16, 2019 - click here for full report.

https://refreshfmbeach.com/wp-content/uploads/2018/11/refresh-blvd-logo-horz-289x84.png

This week, the reFRESH Estero Boulevard active work zone is from Lovers Lane to Albatross Street. Motorists should expect travel lanes on Estero Boulevard to be shifted from Lovers Lane south to Albatross Street. Two travel lanes will remain open the majority of the time; however, intermittent lane closures may be necessary. Motorists should use caution. Read full report.

https://refreshfmbeach.com/wp-content/uploads/2018/11/reFRESH-Logo-Wide-250x84.jpg

reFRESH Waterlines crews are installing water main on both sides of Estero Boulevard from Madera Road to Albatross Street and installing connections to side streets. New water main and storm drainage are being installed on Phase 3 side streets. Read full report. 

//refreshfmbeach.com/wp-content/uploads/2019/08/refreshFMBsegmentmap8.30.19.png

Estero Boulevard Project Segment Progress

Monitor construction progress for each segment of the project, including progression of the installation of the water main, sanitary sewer force main, storm drainage, roadway and sidewalks.

Segment 1 - Crescent Street to Lovers Lane100%

sanitary sewer force main

water main *

storm drainage

roadway

sidewalks

Segment 2 - Lovers Lane to Strandview Avenue91%

sanitary sewer force main

water main *

storm drainage

roadway

sidewalks

Segment 3 - Strandview Avenue to Lanark Avenue46%

sanitary sewer force main

water main *

storm drainage

roadway

sidewalks

Segment 4 - Lanark Avenue to Albatross Street - Future Segment31%

sanitary sewer force main

water main *

storm drainage

roadway

sidewalks

Segment 5 - Albatross Street to Bay Beach Lane - Future Segment0%

Segment 6 - Bay Beach Lane to the end of the island - Future Segment0%

* Water main construction is handled by the Town of Fort Myers Beach with the reFRESH Fort Myers Beach Waterlines Project and progress may be completed prior to the reFRESH Estero Boulevard Project segment beginning.