The reFRESH Estero Boulevard active work zone is from Albatross Street to the end of the island. Two travel lanes will remain open the majority of the time, however, intermittent lane closures may be necessary. Motorists should use caution.
The Town of Fort Myers Beach continues to replace water main and install storm drainage improvements on town side streets throughout the island as part of the Waterlines Replacement Program.
Monitor construction progress for each segment of the project, including progression of the installation of the water main, sanitary sewer force main, storm drainage, roadway and sidewalks.
Segment 1 - Crescent Street to Lovers Lane100%
Segment 2 - Lovers Lane to Strandview Avenue100%
Segment 3 - Strandview Avenue to Lanark Avenue100%
Segment 4 - Lanark Avenue to Albatross Street 100%
Segment 5 - Albatross Street to Bay Beach Lane99%
Segment 6 - Bay Beach Lane to the end of the island99%
* Water main construction is handled by the Town of Fort Myers Beach with the reFRESH Fort Myers Beach Waterlines Project and progress may be completed prior to the reFRESH Estero Boulevard Project segment beginning.
Questions? We're here to help! Submit your questions through our contact form.
Phone: 239-337-1071 | Toll Free: 1-877-496-1076 | Email: [email protected]
All information and graphics are subject to change. © Copyright 2018 reFRESH Estero Boulevard