    water main • sanitary sewer force main •  storm drainage • sidewalk and roadway streetscape

    Learn More

The Estero Boulevard Improvements Project is completed!
Click Here
to see a video (and more) of the Ribbon Cutting Ceremony held on March 30, 2022.

Click here for the Latest News and Documents.

http://refreshfmbeach.com/wp-content/uploads/2018/11/refresh-blvd-logo-horz-289x84.png


The reFRESH Estero Boulevard active work zone is from Albatross Street to the end of the island.  Two travel lanes will remain open the majority of the time, however, intermittent lane closures may be necessary.  Motorists should use caution.

http://refreshfmbeach.com/wp-content/uploads/2018/11/reFRESH-Logo-Wide-250x84.jpg


The Town of Fort Myers Beach continues to replace water main and install storm drainage improvements on town side streets throughout the island as part of the Waterlines Replacement Program.

https://refreshfmbeach.com/wp-content/uploads/2022/02/refreshFMBsegmentmap_2_18_22_Fixed.jpg

Estero Boulevard Project Segment Progress

Monitor construction progress for each segment of the project, including progression of the installation of the water main, sanitary sewer force main, storm drainage, roadway and sidewalks.

Segment 1 - Crescent Street to Lovers Lane100%

sanitary sewer force main

water main *

storm drainage

roadway

sidewalks

Segment 2 - Lovers Lane to Strandview Avenue100%

sanitary sewer force main

water main *

storm drainage

roadway

sidewalks

Segment 3 - Strandview Avenue to Lanark Avenue100%

sanitary sewer force main

water main *

storm drainage

roadway

sidewalks

Segment 4 - Lanark Avenue to Albatross Street 100%

sanitary sewer force main

water main *

storm drainage

roadway

sidewalks

Segment 5 - Albatross Street to Bay Beach Lane99%

sanitary sewer force main

water main *

storm drainage

roadway

sidewalks

Segment 6 - Bay Beach Lane to the end of the island99%

sanitary sewer force main

water main *

storm drainage

roadway

sidewalks

* Water main construction is handled by the Town of Fort Myers Beach with the reFRESH Fort Myers Beach Waterlines Project and progress may be completed prior to the reFRESH Estero Boulevard Project segment beginning.

Questions? We're here to help! Submit your questions through our contact form.