Each week, the Construction Look Ahead is posted to provide updates for construction progress on the reFRESH Estero Boulevard and reFRESH Waterlines Projects. Click on the button to view the latest update.
Segment 1 - Crescent Street to Lovers Lane100%
November 2015 – March 2017
Segment 2 - Lovers Lane To Strandview Ave100%
April 2017 – March 2020
Segment 3 - Strandview Ave To Lanark Ave100%
February 2019 – August 2021
Segment 4 - Lanark Avenue To Albatross Street100%
February 2019 – August 2021
Segment 5 - Albatross Street To Bay Beach Lane99%
August 2020 – In Progress
Segment 6 - Bay Beach Lane To End Of The Island99%
August 2020 – In Progress
Phase 1 - Crescent Street to Lovers Lane100%
July 2015 - March 2016
Phase 2 - Lovers Lane to Madera Road100%
April 2017 - March 2018
Phase 3 - Madera Road to Albatross Street100%
September 2018 - March 2020
Phase 4 - Albatross Street to end of island100%
September 2019 – January 2021