Estero Blvd - Segment 1 Details

Segment 1: Crescent Street to Lovers Lane

https://refreshfmbeach.com/wp-content/uploads/2018/11/refresh-blvd-logo-horz-289x84.png

The right-of-way (ROW) in the first segment of the project–from Crescent Street to Lovers Lane–was very limited, typically with no more than 50 feet in width. The reconstructed Estero Boulevard in this section provides:

  • 10-foot travel lanes in each direction marked with bicycle “sharrows” for shared use
    by bicyclists and motorists (this is due to the limited right-of-way)
  • 11-foot center turn lane
  • 9-foot-wide sidewalks on both sides of the road
  • Trolley stops
//refreshfmbeach.com/wp-content/uploads/2018/11/Segment-1.png

Segment 1 - Crescent Street to Lovers Lane100%

sanitary sewer force main

water main *

storm drainage

roadway

sidewalks

* Water main construction is handled by the Town of Fort Myers Beach with the reFRESH Fort Myers Beach Waterlines Project and progress may be completed prior to the reFRESH Estero Boulevard Project segment beginning.

Progress Status: Complete

Construction for Segment 1 began in November 2015 and completed in March 2017. Below is a rendering of the new Estero Boulevard from Crescent Street to Lovers Lane along with a diagram of the new road and sidewalk layout. In addition, you can view the roll plot for this segment. 

//refreshfmbeach.com/wp-content/uploads/2018/12/aerial-view-crop-u45007.jpg
//refreshfmbeach.com/wp-content/uploads/2018/12/center-lane-drainage.jpg
//refreshfmbeach.com/wp-content/uploads/2018/12/infographic-segment-1.jpg

Roll Plot

Click here for a larger view of the Segment 1 Roll Plot.

//refreshfmbeach.com/wp-content/uploads/2019/03/SEG-1-ROLL-PLOT-small-1.png

Questions? We're here to help! Submit your questions through our contact form.